What a WIP schedule actually tells you (and why your banker cares)
Your WIP schedule is one of the most useful pieces of paper your construction business produces all month. It tells you whether jobs are making money. It tells you whether billings are keeping up with the work. And whether you like it or not, it tells your banker a lot about how you run your business.
So, let’s talk about what’s in there, what it really shows, and why your loan officer pulls it out before just about anything else.
What is a WIP schedule?
A work-in-progress schedule is a project-by-project financial report. For each active job, it lays out how much work you’ve completed, how much you’ve billed, what the job will probably cost by the time it wraps, and whether you’re sitting overbilled or underbilled today.
Boiled down to one question: Is the job on track, or are the numbers starting to drift?
What does a WIP schedule show you?
A standard WIP schedule pulls together a handful of data points per job:
Total contract value
Costs incurred to date
Estimated costs to complete
Percent complete
Revenue earned to date
Billings to date
Overbilling or underbilling position
Put those together, and you’ve got a snapshot of progress and profitability on every job at the same moment in time. Read it carefully, and you’ll catch profit fade, slow billings, missing change orders, and cost overruns before any of them turn into real problems. The AICPA calls WIP schedules the blueprint of solid construction accounting, and for good reason.
A quick example
Imagine a $1 million job that’s 70% complete, but you’ve only billed $500,000. Your WIP shows you’re underbilled by $200,000. Not necessarily a problem, but a chunk of cash is sitting in work you’ve already put in place. That’s the kind of thing your banker wants to see and understand.
Why does your banker care about your WIP schedule?
Bankers use your WIP schedule for two reasons:
It tells the bank whether your financial statements are trustworthy.
It tells them whether your project performance can support the debt you’re carrying or asking for.
A clean, current WIP signals that you can estimate jobs, manage costs, and run a tight shop. A sloppy one signals the opposite. Bankers also pay close attention to your billing position, because over- and underbillings are where cash trouble tends to hide. Heavy underbillings can mean you’re financing your customer’s project. Heavy overbillings can mean you’re financing your own operations with money you haven’t really earned yet.
When your numbers tie back to real performance on real jobs, your credit line, your bonding capacity, and your covenant compliance all get easier.
Red flags bankers watch for
When a lender opens your WIP, certain patterns put them on edge. Among the worst offenders:
Underbillings that keep growing across multiple jobs
Overbillings running above roughly 15% of costs incurred
Profit fade as jobs progress
Projected margins well above what your historicals show
Percent complete that doesn’t match what your project managers say in the field
Jobs parked above 90% complete for months with no closeout
Big surprise write-downs at year-end instead of small, timely adjustments
One oddball job won’t sink you, but a pattern across jobs will.
How to keep your WIP accurate every month
None of this is rocket science—it’s habit. Here’s what disciplined contractors do:
Close the WIP as part of your monthly close, not whenever you get around to it.
Update contract values for approved change orders before finalizing anything.
Refresh estimated cost to complete with input from the project managers, not just from accounting.
Reconcile WIP totals to the general ledger and tie out your over- and underbilling balances.
Use one standard template with locked formulas across every job.
Sit down monthly with your PMs and walk through the schedule job by job.
Look for the easy errors: jobs over 100% complete, closed jobs still hanging on, costs charged to the wrong bucket.
Contractors who do this consistently rarely get caught off guard, and they rarely surprise their bankers either.
Get more value from your WIP schedule
A strong WIP schedule earns your banker’s trust, sharpens your decision-making, and protects your margins. The team at Kinexus helps contractors build reporting processes that hold up under scrutiny and make every credit conversation easier. Reach out to talk through your current WIP process and where it could be working harder for you.